1. Production server was down…

    …yesterday morning for about 4 hours. A process that was only supposed to affect new sites unexpectedly prevented UW-Madison and UW-Whitewater users from logging in. Server admins will be putting a more robust procedure in place to avoid this type of error in the future.

  2. Production go-live…

    …has been scheduled for Saturday, October 10, 2020.

  3. The default provisioning application…

    …has passed user acceptance testing on the Dev server (as of 9/14), and is ready to deploy to the production server once it goes live.

  4. MFA has been deployed to Dev server…

    …for additional testing.

  5. Migration timetable has been extended…

    …to resolve issues raised in testing MFA and automated provisioning.

  6. URL redirects have passed testing.