News 2018
-
Wrapping up UAT and Roadshows
August 17, 2018
The team has finished 3 of 4 roadshows. Thanks to all institutional folks who came out, and who will for the last one! User Acceptance Testing (UAT) is finishing up […]
-
Preparing for User Acceptance Test
June 29, 2018
The environments have been delivered after our trial go-live – Test Move 2. Sighs of relief need to wait, while we do our post Test Move regression testing next week. […]
-
Wrapping up System Testing
May 25, 2018
The project team is facing a big target – Test Move 2! A test move is a test to verify all our procedures to upgrade from 9.1 to 9.2 work […]
-
Planning for Campus Outreach
May 11, 2018
Beginning in mid-July, the SFS 9.2 upgrade team will be bringing information in the forms of overviews, demos, and hands-on time to campus users. One of this month’s big pushes […]
-
Development winding down.
April 18, 2018
Our planned development is winding down. Testing activities have dramatically increased. And the team is working with integration partners to make sure that messages sent to outside systems still work. […]
-
Heads Down!
March 28, 2018
The project team is working heads-down on Development, Configuration, Unit Testing, and System Testing. Great job, everyone! We have a couple months in front of us dedicated to Testing the […]
-
System Test Begun
March 14, 2018
The project moved into System Test last week. The module teams are working diligently to make sure the fixes and improvements coming your way are working and ready. The team […]
-
Test Move Underway
February 16, 2018
Our activity to practice our move to production, Test Move 1, is currently underway. It will wrap up by the end of February. This is the first to three planned […]
-
Scope Complete!
February 2, 2018
The project team has concluded the scope considerations, and our Executive Sponsors have approved! In the next week, stakeholders can expect an email from our Executive Sponsors indicating some of […]
-
Scope Finalization Pending
January 4, 2018
The subject-matter-experts, with institutional representation, have done very well presenting recommendations. We are reviewing those recommendations based on the constraints of the project, and will begin communicating scope later this […]